Chula Vista ADU Permit Process: 8 Steps, Real 2026 Fees & Pre-Submittal Checklist

Updated May 12, 2026 — fees verified against City of Chula Vista FY 2025–26 fee schedule

At a Glance: Chula Vista ADU Permit Facts (2026)

  • Review clock: 60 calendar days after a complete submittal is accepted (state mandate)
  • Permit fee — City Standard detached: $3,951 base (first 500 sq ft) + $7.84/sq ft above 500
  • Permit fee — custom detached: $4,963 base (first 500 sq ft) + $9.83/sq ft above 500
  • Impact fees (detached): ~$6,960 transportation + $3,399–$7,064 parks + sewer
  • School fee (Sweetwater USD): $5.19/sq ft for ADUs 500 sq ft and up
  • Soils waiver: available for parcels with existing approved geotechnical report on file
  • Owner-occupancy: not required for standard ADUs; required for JADUs
  • Max size: 1,200 sq ft detached or attached; 500 sq ft JADU
  • Portal: ProjectDox (online) or in-person at 276 Fourth Avenue, Chula Vista
Completed detached ADU in a Chula Vista backyard alongside the primary residence

A completed detached ADU in Chula Vista. The permit process typically takes 3–6 months; construction adds another 3–5 months.

Chula Vista's ADU permit process runs on California's mandatory 60-day ministerial review clock — but the clock only starts when your submittal is complete. Most first-time applicants lose weeks to missing documents, unclear setback math, or failing the soils-assessment threshold. This guide walks every stage, names every fee, and tells you exactly what lands on a permit technician's desk.

All fees are from the City of Chula Vista's FY 2025–26 adopted fee schedule. Impact fees are from the city's Development Impact Fee program and are verified as of the publication date above.

Navigating the permit process without a builder who knows Chula Vista?

SnapADU has guided hundreds of Chula Vista ADU projects through Development Services. They handle the application, correction cycles, and inspection scheduling.

Get a free quote from SnapADU →

Affiliate link — we may earn a commission at no cost to you. Full disclosure

Do I need a building permit for an ADU in Chula Vista?

Yes — every ADU type requires a building permit from Chula Vista's Development Services Department. There is no permit-exempt path for ADUs. This includes:

Ministerial vs. discretionary review

California law (AB 68, SB 13, AB 671, and AB 3182) classifies ADU permit review as ministerial — meaning the city reviews for code compliance only and cannot reject an application for policy or neighborhood reasons. There is no design review, no public hearing, and no discretionary approval. If your plans meet the objective standards (size, setbacks, height, lot coverage), the city must approve.

The 60-day review clock begins the moment Development Services deems your submittal complete. If the city fails to act within 60 days, the application is approved by operation of law under California Government Code §65589.5(j).

The Chula Vista ADU permit process: 8 steps

Infographic showing the 8 steps of the Chula Vista ADU permit process from zoning check to Certificate of Occupancy

Step 1 — Confirm Chula Vista city limits and zoning eligibility

Start at the Chula Vista GIS map or the San Diego County Assessor Parcel lookup. Verify your parcel is inside city limits — not in unincorporated San Diego County, which uses county ADU rules instead. Then check your zoning designation.

ADUs are permitted in all residential zones (R-1 through R-3), residential-planned zones, and most mixed-use zones with a residential component. Your primary dwelling must be legally permitted and in good standing — an address with open code violations can delay or block your ADU application.

Watch for: Properties in the Bayfront Specific Plan area (west of I-5 near the bay) have additional design and environmental review requirements. Hillside parcels in eastern Chula Vista (Otay Ranch, Rolling Hills Ranch) may face soils constraints — see Step 3.

Step 2 — Choose your ADU type before drawing plans

The ADU type you choose affects your permit fees, required documents, and construction cost by tens of thousands of dollars. Make this decision before hiring a designer.

Decision diagram showing three Chula Vista ADU paths: City Standard, custom/non-standard, and garage/structure conversion
ADU TypeBest forBase permit feeTypical design cost
City Standard detachedFlat or gently sloped lots, standard slab foundation$3,951$0–$5,000 (pre-approved plans)
Custom/non-standard detachedComplex lots, hillsides, architectural customization$4,963$10,000–$25,000+
Attached ADU (addition)Private entrance, shared wall with primary home$2,380 (first 300 sq ft)$8,000–$18,000
Garage conversion ADUExisting attached or detached garage$1,604 (first 400 sq ft)$5,000–$12,000
JADU (Junior ADU)Interior room within primary dwelling, owner-occupant$1,391$3,000–$8,000

Design costs are estimates. City Standard applicants use city-provided pre-approved structural plans, eliminating most engineering fees.

Step 3 — Attend a free pre-application meeting (optional but recommended)

Chula Vista's Development Services Department offers free pre-application conferences for ADU projects. Bring your parcel number, a rough sketch of the proposed ADU location, and your selected ADU type. Staff will:

  • Flag overlay zones (Bayfront, Otay Ranch Planned Community, VHFHSZ fire zones)
  • Check for existing soils reports on file — your soils waiver opportunity
  • Confirm setback requirements specific to your parcel and zone
  • Identify required agency referrals (Fire Department, Engineering, Stormwater)

The soils waiver is the most valuable thing a pre-application meeting surfaces. Many Chula Vista tracts — especially in Otay Ranch and Eastlake — have existing geotechnical reports on file. If Development Services confirms your parcel is covered, you skip a $2,500–$6,000 soils investigation and 4–8 weeks of geotechnical lead time.

Step 4 — Prepare plans, forms, and required documents

A complete Chula Vista ADU permit submittal requires the following. Missing any item triggers an incompleteness notice and delays your 60-day clock.

DocumentNotes
Title sheetScope of work, applicable codes, occupancy classification
Site planDimensioned setbacks, lot coverage %, existing and proposed structures, utilities
Floor plans1/4" scale minimum, room labels, door/window schedules
ElevationsAll four sides, with finished grade, ridge height, and existing grade shown
Foundation/structural plansPre-approved plans cover this for City Standard; custom requires engineered
Title 24 energy complianceHERS rater or CF1R form; required for all new conditioned space
Building Permit ApplicationCity form; include licensed contractor info or owner-builder declaration
Stormwater Applicability ChecklistRequired by Engineering; determines if storm water management plan is needed
School fee certificationReceipt from Sweetwater USD confirming fees paid or exemption confirmed
Soils report (or waiver documentation)Ask at pre-application meeting whether existing report covers your parcel
City Standard shortcut: Chula Vista's pre-approved plan library provides the title sheet, floor plans, elevations, and structural details for common 1-story ADU footprints. You still need a site plan, energy compliance, and project-specific forms — but you skip custom architectural and structural engineering drawings.

Step 5 — Submit permit application via ProjectDox or in-person

Chula Vista accepts ADU permit applications electronically via ProjectDox (the city's online permit portal) and in person at:

City of Chula Vista Development Services
276 Fourth Avenue
Chula Vista, CA 91910
Monday–Friday, 8:00 AM–5:00 PM

At submission, pay the initial plan-check deposit (typically 50–75% of the total permit fee). Development Services reviews for completeness within 5 business days. If the submittal is incomplete, you receive a correction notice and must resubmit — the 60-day clock has not started yet.

Once accepted as complete, you receive a permit number and the 60-day review clock begins. Track status in ProjectDox or call (619) 691-5272.

Step 6 — Clear plan review: the 60-day ministerial clock

City Standard applications typically clear first review in 3–5 weeks. Custom detached ADUs average 6–10 weeks for a first response. During review:

  • Multiple city departments review simultaneously (Building, Engineering, Fire, Stormwater)
  • Correction notices are sent via ProjectDox with a response deadline
  • Each correction cycle must be resolved; the cumulative review time counts against the 60-day window
  • If the city exhausts the 60 days without action, the permit is approved by operation of law
Responding to corrections: Turnaround time on correction responses directly affects your total timeline. Aim to respond within 5 business days of each correction notice. Slow responses allow the city to extend review and your project sits in queue.

Step 7 — Pay fees and receive approved permits

After plan approval, Development Services issues a fee payment notice. You must pay the remaining permit fees, any outstanding impact fees, and school fee certification (which must be paid directly to Sweetwater USD before the city releases the permit). Once all fees are cleared, you receive the approved permit set — either as stamped paper or digital PDFs through ProjectDox.

Keep approved plans on-site throughout construction. The inspector will verify work against the stamped set at each inspection stage.

Step 8 — Build, pass inspections, and receive Certificate of Occupancy

Schedule inspections through the city's automated system or ProjectDox. Chula Vista typically books 1–3 business days out. Required inspection stages:

  1. Foundation/pre-pour (before concrete is placed)
  2. Framing (after structural framing, before insulation)
  3. Rough electrical, plumbing, and HVAC (before wallboard)
  4. Insulation (before wallboard)
  5. Wallboard (before taping and texture)
  6. Final inspection (all finishes complete, utilities connected)

After the final inspection passes, the city issues a Certificate of Occupancy (C of O). The ADU is legally habitable and can be legally rented. Update your insurance policy before the first tenant moves in.

Ready to start your Chula Vista ADU?

SnapADU manages the entire permit process — from pre-application to final C of O — for Chula Vista homeowners. Their team knows the city's review cycles and correction patterns from hundreds of completed projects.

Get your free SnapADU quote →

Affiliate link — disclosure

How long does the Chula Vista ADU permit process take?

The timeline varies significantly by ADU type and submittal quality. Here are realistic estimates based on Chula Vista permit data:

PathSubmittal to approvalConstructionTotal project
City Standard (first-time, clean submittal)6–10 weeks14–20 weeks5–8 months
City Standard (with correction cycles)10–16 weeks14–20 weeks7–10 months
Custom detached (no soils issues)12–20 weeks16–24 weeks8–12 months
Custom detached (soils study required)20–28 weeks16–24 weeks10–14 months
Garage conversion / JADU6–12 weeks8–14 weeks4–7 months

These ranges assume a complete, correct first submittal. Every correction cycle adds 2–5 weeks. The biggest time killers are incomplete stormwater documentation, missing energy compliance reports, and soils studies that weren't ordered before design started.

How much do Chula Vista ADU permit fees cost?

Chula Vista uses a tiered fee schedule based on ADU type and square footage. These figures are from the city's FY 2025–26 Comprehensive Fee Schedule.

Building permit fees by ADU type

ADU TypeBase fee (first sq ft tier)Additional sq ft rate
City Standard detached$3,951 (first 500 sq ft)+ $7.84/sq ft above 500
Custom / non-standard detached$4,963 (first 500 sq ft)+ $9.83/sq ft above 500
Attached ADU (addition)$2,380 (first 300 sq ft)+ $7.94/sq ft above 300
Garage / accessory structure conversion$1,604 (first 400 sq ft)+ $4.01/sq ft above 400
JADU (interior conversion)$1,391 (flat fee)N/A

Worked examples: what you'll actually pay at permit

ScenarioSizePermit fee
City Standard studio ADU400 sq ft$3,951
City Standard 1BR ADU650 sq ft$3,951 + (150 × $7.84) = $5,127
City Standard 2BR ADU1,000 sq ft$3,951 + (500 × $7.84) = $7,871
Custom detached 1BR ADU700 sq ft$4,963 + (200 × $9.83) = $6,929
Garage conversion480 sq ft$1,604 + (80 × $4.01) = $1,925

City Standard saves $1,012+ vs. custom — and that's before design fees

On a 1,000 sq ft ADU, City Standard costs $7,871 in permit fees vs. $13,778 custom. Add the design cost difference ($0–$5k vs. $15k–$25k) and City Standard can save $15,000–$25,000 total for standard lots. SnapADU builds exclusively using City Standard where eligible — ask them if your lot qualifies.

See if my lot qualifies for City Standard →

Affiliate link — disclosure

Impact fees and school fees: what adds to the bill

Permit fees are only part of the government cost to build an ADU in Chula Vista. Impact fees and school fees can add $10,000–$20,000 on top of the base permit fee, depending on your ADU type and size.

Transportation development impact fees

ADU TypeTransportation DIF
Detached ADU (any size)$6,960
Attached ADU or JADU (under 500 sq ft)$3,480

Parks development impact fees

ADU SizeParks DIF
0–499 sq ft$3,399
500–999 sq ft$4,661
1,000–1,749 sq ft$7,064
JADUExempt

School fees (Sweetwater USD)

Most of Chula Vista falls within the Sweetwater Union High School District (SUHSD). Sweetwater charges school fees on new residential construction under California Education Code §17620:

Sewer capacity fees

Sewer connection and capacity fees vary by meter size and whether the ADU connects to an existing lateral or requires a new connection. Expect $2,000–$8,000 for a new sewer lateral; check with Chula Vista Public Works Engineering at the pre-application meeting.

Realistic all-government cost for a 650 sq ft detached City Standard ADU

Fee categoryAmount
Building permit fee (City Standard, 650 sq ft)$5,127
Transportation DIF (detached)$6,960
Parks DIF (500–999 sq ft)$4,661
Sweetwater school fee (650 × $5.19)$3,374
Sewer capacity (estimate, new lateral)$3,500
Total government fees (estimated)~$23,622

Fees as of FY 2025–26; sewer capacity is an estimate and varies by connection type. Confirm all fees with Chula Vista Development Services before budgeting.

How 2026 California ADU laws apply in Chula Vista

California state law sets a floor for ADU rights that cities must meet or exceed. Chula Vista's local rules comply with all current state mandates:

State lawWhat it doesChula Vista application
AB 68 / SB 13Eliminates most ADU restrictions; mandates ministerial reviewChula Vista compliant; 60-day clock enforced
AB 671Sets 60-day review deadline; deemed-approved ruleApplies; city must approve or deny within 60 days of complete submittal
AB 3182Voids HOA ADU prohibitionsHOAs in Otay Ranch, Eastlake, Rolling Hills Ranch cannot block ADUs
SB 9Allows lot splits and duplexes on SFR lotsAvailable in Chula Vista; each SB 9 lot can have its own ADU
SB 1186 (retroactive legalization)Streamlines permitting of existing unpermitted ADUsAvailable; requires full code compliance inspection
AB 2533Lowers penalty for unpermitted ADUs built before 2018Reduces fines for pre-2018 structures being retroactively permitted

Chula Vista ADU development standards (size, setbacks, height, parking)

Size limits

Setbacks

Height limits

Parking

Property-specific risks that complicate permits

Bayfront Specific Plan area

Properties west of I-5 in the Bayfront Specific Plan area face additional design review requirements. ADUs in this zone must comply with Bayfront design guidelines (materials, massing, landscaping) on top of standard code requirements.

Soils and geotechnical constraints

Eastern Chula Vista has expansive clay soils and hillside conditions common in Otay Ranch, Eastlake, and Rolling Hills Ranch. These require a site-specific soils investigation unless a prior report covers your parcel. Ask Development Services to check at your pre-application meeting — many newer tracts have existing reports.

Fire Hazard Severity Zones (VHFHSZ)

Parcels in state-designated Very High Fire Hazard Severity Zones must use Class A fire-rated roofing, ember-resistant vents, non-combustible siding within 5 feet of the exterior wall, and comply with defensible space requirements. These add cost but do not change the 60-day review timeline.

HOA CC&Rs in planned communities

Eastlake, Otay Ranch, Rolling Hills Ranch, and other master-planned communities have HOAs with architectural review boards. California law (Civil Code §4751) prohibits HOAs from blocking ADUs outright, but they can impose reasonable design standards. Build time for HOA architectural review into your pre-construction schedule — typically 30–60 days.

Steep slopes and retaining walls

Hillside lots common in eastern Chula Vista often require grading permits, retaining walls, and drainage engineering separate from the ADU building permit. These can add $15,000–$50,000 in site work costs and 4–12 additional weeks to the permit timeline.

Working with a builder who knows Chula Vista's permit quirks

SnapADU has completed ADU projects across Chula Vista — from Bayfront-adjacent parcels to Otay Ranch hillside lots. They know which Chula Vista tracts have existing soils reports on file, how to navigate the city's correction cycle, and which sub-contractors pass Chula Vista inspections reliably.

Explore SnapADU for your Chula Vista project →

Sponsored link — see our partner vetting policy

How Chula Vista homeowners pay for ADUs

With total project costs for a detached Chula Vista ADU typically ranging from $180,000–$340,000, most owners combine a primary financing vehicle with equity built during construction:

See our ADU financing guide for a full comparison of each option with qualification thresholds and lender examples.

Why permits get delayed — and how to prevent it

Delay causePrevention
Incomplete submittal (most common)Use the pre-submittal checklist in this guide; attend the free pre-application meeting
Missing soils reportCheck for existing on-file reports at pre-application meeting; order soils study before design starts if not covered
Energy compliance gapsHire a Title 24 consultant early; use a form that matches your HVAC and insulation spec
School fee documentation missingContact Sweetwater USD before submittal; confirm fee amount or exemption in writing
Slow correction responsesRespond to every correction notice within 5 business days; assign an experienced local designer or builder who monitors ProjectDox
Stormwater plan required but not includedComplete the Stormwater Applicability Checklist at submittal; have Engineering review it if your lot has drainage complexity

Pre-submittal checklist: what to confirm before you click “submit”

Visual pre-submittal checklist for a Chula Vista ADU permit application

Run through this checklist before submitting to Development Services. Every unchecked item is a likely incompleteness notice.

Confirmed property is inside Chula Vista city limits (not unincorporated county)
Verified residential zoning designation and ADU eligibility
Selected ADU type (City Standard / custom / attached / garage conversion / JADU)
Held or scheduled pre-application meeting with Development Services
Confirmed soils report status — existing on file or new report ordered
Completed Title Sheet with scope of work, codes, and occupancy classification
Site plan drawn with dimensioned setbacks, lot coverage %, all structures labeled
Floor plans at 1/4" scale minimum with room labels and door/window schedules
Elevations on all four sides with finished grade, ridge height, existing grade
Foundation and structural plans (City Standard: pre-approved set; custom: engineered)
Title 24 energy compliance report (CF1R or HERS rater documentation)
Completed Building Permit Application with licensed contractor or owner-builder declaration
Stormwater Applicability Checklist completed and signed
Sweetwater USD school fee paid or exemption confirmed in writing
If applicable: Fire Department clearance, Engineering grading comments, HVAC load calculations

Honest tradeoffs: is a Chula Vista ADU worth it?

Chula Vista's ADU permit process is well-structured compared to many California cities — the City Standard program, free pre-application meetings, and online portal make it approachable. But the full government fee stack ($20,000–$30,000) and 3–6 month permit timeline mean this is a serious undertaking, not a quick project.

AdvantageLimitation
City Standard program reduces design costs by $10,000–$20,000Impact fees ($10,000–$14,000) add significantly to total cost
Free pre-application meetings surface issues earlySoils requirements on hillside lots add 6–12 weeks and $3,000–$6,000
60-day ministerial clock prevents indefinite delaysIncomplete submittals restart the clock and add months
Strong rental market (near SDSU South Bay, Navy bases)Sweetwater school fees on larger ADUs are among the highest in SD County
HOAs cannot block ADUs under CA lawHOA architectural review adds 30–60 days before city submittal

What we verified

ClaimSourceVerified
City Standard permit fee: $3,951 base / $7.84 per sq ft above 500City of Chula Vista FY 2025–26 Fee ScheduleMay 2026
Custom detached permit fee: $4,963 base / $9.83 per sq ft above 500City of Chula Vista FY 2025–26 Fee ScheduleMay 2026
Transportation DIF: $6,960 detached / $3,480 JADUCity of Chula Vista Development Impact Fee ProgramMay 2026
Parks DIF: $3,399–$7,064 by size tierCity of Chula Vista Parks Development Impact Fee ScheduleMay 2026
Sweetwater USD school fee: $5.19/sq ftSweetwater Union High School District §17620 fee scheduleMay 2026
60-day ministerial review mandateCalifornia Government Code §65852.2(a)(3); AB 671May 2026
HOA prohibition on ADUs void under Civil Code §4751California Civil Code §4751; AB 3182May 2026
4-foot rear/side setback minimumCalifornia Government Code §65852.2(a)(1)(D); Chula Vista CVMC §19.58.022May 2026

Get your Chula Vista ADU project started today

SnapADU offers free consultations for Chula Vista homeowners. They'll confirm your City Standard eligibility, estimated permit fees, and construction timeline before you commit to anything.

Schedule a free consultation with SnapADU →

Affiliate link — we may earn a commission at no cost to you. Full disclosure

Prefer to go deep on your own first?

The ADU Starter Kit includes a project budget template, permit timeline tracker, contractor vetting checklist, and a financing comparison worksheet — everything to structure your research before your first builder call.

Get the free ADU Starter Kit →

Frequently asked questions

Do I need a building permit for an ADU in Chula Vista?

Yes. All ADU types — detached, attached, garage conversion, and JADU — require a building permit from the City of Chula Vista Development Services Department. Operating an unpermitted ADU risks stop-work orders, code-violation liens, and required demolition.

How long does the Chula Vista ADU permit process take?

Plan for 3–6 months total from completed application submission to permit issuance, plus 3–5 months of construction. City Standard (pre-approved plan) projects routinely run on the low end. Custom detached ADUs with geotechnical requirements average 5–6 months to permit.

What is the 60-day ministerial review clock?

California law (AB 68, SB 13, AB 671) requires cities to approve or deny a complete ADU permit application within 60 calendar days. The clock starts when Chula Vista deems your submittal complete. If the city misses the deadline, the application is deemed approved by operation of law. This rule applies to all ADU types.

How much does an ADU building permit cost in Chula Vista?

City Standard detached ADU permit fees start at $3,951 for the first 500 sq ft, plus $7.84 per sq ft above 500. Custom/non-standard detached starts at $4,963 for the first 500 sq ft, plus $9.83 per sq ft above 500. Garage conversions start at $1,604. These are permit-only fees; impact fees (transportation $6,960, parks $3,399–$7,064) and school fees ($5.19/sq ft) are separate.

What is the City Standard ADU program in Chula Vista?

Chula Vista's City Standard ADU program offers pre-approved plan sets — one-story, up to 1,200 sq ft, with prescriptive structural details — that qualify for lower permit fees ($3,951 vs. $4,963+ base) and faster review. Applicants still need a site-specific soils assessment, but City Standard plans bypass custom structural engineering, saving $5,000–$15,000 in design costs.

Can I build an ADU without a soils report in Chula Vista?

Chula Vista requires a site-specific soils assessment for most ADU projects, but the city grants a soils-study waiver for properties that already have an approved geotechnical report on file. This is common in newer tract developments like Otay Ranch and Eastlake. Ask Development Services to check your parcel's existing soils data at your pre-application meeting.

What is a JADU and how does it differ from a standard ADU?

A Junior ADU (JADU) is a unit of 150–500 sq ft carved out of the existing primary dwelling's footprint. JADUs require an owner-occupancy covenant recorded on title, share a bathroom with the main house (or have an efficiency kitchen), and pay lower permit fees ($1,391). JADUs are exempt from most impact fees and may qualify for school-fee exemptions.

Does Chula Vista charge impact fees on ADUs?

Yes, Chula Vista charges transportation impact fees ($6,960 for detached ADUs, $3,480 for JADUs and attached ADUs under 500 sq ft) and parks development fees ($3,399–$7,064 depending on ADU size). Sewer capacity fees vary by meter size. JADUs are exempt from parks fees.

Do Sweetwater schools charge fees on every Chula Vista ADU?

Sweetwater Union High School District charges $5.19 per sq ft of new residential construction. ADUs of 500 sq ft or more typically pay. JADUs and internal conversions of existing permitted space may qualify for exemption under California Education Code §17620(b). Confirm with the district before permit submission.

Can my HOA stop me from building an ADU in Chula Vista?

No. Under California Civil Code §4751, HOAs cannot prohibit ADUs or JADUs on single-family lots. They may impose reasonable design standards (materials, colors, screening) but cannot use those standards to effectively prohibit construction. HOA approval delays do not pause the city's 60-day review clock.

What are the size limits for a Chula Vista ADU?

Detached ADUs can be up to 1,200 sq ft. Attached ADUs are capped at 50% of the primary dwelling's living area, up to 1,200 sq ft. JADUs are limited to 500 sq ft. Chula Vista also follows the state 800-sq-ft minimum entitlement: if your setbacks or lot constraints would otherwise limit an ADU below 800 sq ft, the city must still allow up to 800 sq ft.

Do I need to be an owner-occupant to build an ADU in Chula Vista?

No. California law (AB 68) eliminated the owner-occupancy requirement for standard ADUs. As of 2025, owner-occupancy is only required for JADUs (Junior ADUs), which must have an owner-occupancy covenant recorded on title. Standard detached and attached ADUs can be built and rented by non-owner landlords.

Can I build more than one ADU on my Chula Vista property?

Yes. California allows one attached or detached ADU plus one JADU on a single-family lot. On multifamily properties, the state allows two detached ADUs plus conversions of existing non-livable space (garages, storage, utility rooms). Chula Vista follows state minimums.

What happens if I build an ADU without a permit in Chula Vista?

Unpermitted ADUs are subject to code-violation orders, daily fines up to $1,000, and liens on the property. The city can require you to demolish the structure or obtain a retroactive permit (often harder and more expensive than getting one upfront). Retroactive legalization under California's SB 1186 program is available but requires full compliance with current building code, which may mean opening walls for inspection.